Skip to main content

Want to take over the management of your building?

Our E-Learning platform has modules for leaseholders looking to manage their own building using a RTM company.

Find out more here

What should the second notice of estimates for major works contain?

The second notice  for major works (notice of estimates) must be sent by the landlord to each leaseholder and the recognised tenants association, if there is one.

Such  notice must include details of at least two estimates that the landlord has obtained. One of the estimates must be from a contractor wholly unconnected with the landlord.

The landlord must invite observations in writing within 30 days and must have regard to any observations received.


More information you might find useful:

Still not found the answer?

Contact LEASE to have your enquiry dealt with by one of our experienced advisers

LEASE is governed by a board, appointed as individuals by the Secretary of State for the Department for Levelling Up, Housing & Communities.