What should the second notice of estimates for major works contain?

The second notice  for major works (notice of estimates) must be sent by the landlord to each leaseholder and the recognised tenants association, if there is one.

Such  notice must include details of at least two estimates that the landlord has obtained. One of the estimates must be from a contractor wholly unconnected with the landlord.

The landlord must invite observations in writing within 30 days and must have regard to any observations received.